Friday, July 06, 2007

operation big house

Don has come up with a schedule for the rest of the summer. In theory, this schedule will make it so that the upstairs subfloors are done by the beginning of September, although I believe some of that depends on how much Don and his dad are willing to work during the week in August. So here's "Operation Big House" (apparently that's what the family used to call our house in Don's childhood, and he still calls it that). Creative spelling has been corrected by yours truly.

Operation Big House (7/5/07)

July 7: Finish mudroom demo / Fix downstairs bathroom waterlines / Clean up downstairs wood and tools


July 8-12: Pack upstairs / Move boxes into storage


July 9-12: HVAC Downstairs installation


July 13: Dumpster change out


July 14: Clean the downstairs (rest of plaster/nails/etc) / Tarp downstairs ceiling and windows / Move downstairs / Tarp downstairs “walls” / Run downstairs temp electric


July 15: Clean out attic / Buy trash cans for makeshift dumpster chute


July 16-20: Remove landing window / Build temporary stairway landing / Assemble dumpster chute

July 20: Remove upstairs doors / Remove upstairs blinds / Turn off upstairs water / Turn off upstairs electric

July 21: Demo Day 2 (which many of you should now have the evite for! If you don't have it and you want it, let me know.)


July 22: Install new attic trapdoor ladder / Clean the upstairs (rest of plaster/nails/etc)


July 23 or 30: HVAC Upstairs installation begins


Beginning August: Window installation